Major Loss Insurance Projects
Multiple
How Savil Projects delivered multiple major loss insurance projects from the January 2020 hailstorm including initial consultancy to relevant stakeholders.
Our Construction team work with you to manage and deliver major loss insurance works on your commercial building. We work with all internal stakeholders, assessors, insurers, superintendents, quantity surveyors, architects, and designers to offer flexible options, such as staged commercial construction on occupied sites with high-profile tenants.
Savil Projects were engaged to complete major loss insurance works to the following commercial buildings in prominent Canberra locations. Our clients required a timely and cost-effective construction solution that would facilitate the replacement of roofing and roofing components, various facade replacements, windows including textured stained glazing, mechanical units and components, various types of skylights and, all internals of the buildings that were damaged from water ingress from various insurable events including the major hailstorm that hit Canberra in January 2022.
Saint Nicholas Greek Orthodox Church – Kingston
Replacement and a full rebuild of 4 large hand-crafted copper domes, the 50-year-old terracotta roofing tiles, textured stained glass windows, 2 oversized A/C condenser units, entire 15-meter-high ceiling replacement including all insulation panels replaced, all services in the ceiling inspected and replaced if moisture found inside during testing.
Duration: 12 weeks
Barrandi Centre – City West
Complete roof replacement of approximately 2000m2 on 9 storey high building in the CBD, all roofing components and mechanical replaced, copper awning façade replaced and copper blade wall 50m high replaced.
Duration: 10 weeks
National Archives of Australia
Duration: 5 months
Hotel Kurrajong
Duration: 4 weeks
Pharmacy Guild House – Barton (Parliamentary Triangle)
Complete roof and cladding replacement of 2000m2 of roof including entire roof and components, aluminium cladding panels (400m2), all mechanicals replaced including all damaged internal ceilings.
Duration: 12 weeks
RSL Lifecare - Page
Widespread major loss insurance works across nine RSL Lifecare aged care buildings in the suburb of Page, including 1000m2 roof rectification, skylight replacements, mechanical replacements, ceiling and wall replacements including insulation, services inside ceiling spaces, carpet and flooring replacements, painting and furniture replacements.
Duration: 12 weeks
Cretonia House - Oatley Court – Belconnen
Roof and roofing components were replaced for the commercial building in the Belconnen town centre, including perimeter capping and gutters. Roof size 1000m2
Duration: 2 weeks
BWS – Kingston
Complete roof replacement including all roofing components and mechanical systems, 600m2 of hail-damaged commercial roof in Kingston Town Centre.
Duration: 4 weeks
Saint Nicholas Greek Hall - Kingston
Make safe including removing dislodged roofing tiles, complete roof tarped and weight down, removal of all ceiling, insulation, flooring, joinery in kitchen and bathrooms, clearing out to bare shell. Later demolished the building and excavated the site in preparation for a new community hall to be built later in the future.
Duration: 4 weeks
How Savil Projects managed the construction projects with strong attention to detail, time and budget management.
The projects required end-to-end project management and comprehensive construction/roofing works tailored to the stakeholder’s requirements.
All of the projects were conducted at live and occupied sites, allowing Savil Projects to showcase its innovative solutions and exemplary customer service systems tailored to such sites. Although some run-of-the-mill construction companies may consider shutting the buildings down while the project is being completed or simply turning the project down, Savil Projects specialises in continuing to work with building owners/tenants/building management and stakeholders to keep the building operational throughout the works. We do this by going above and beyond in safety management and documentation, high levels of communication and diligent full-time supervision while ensuring the quality and Australian Standards are met every part of the way.
Savil Projects were able to deliver an innovative construction/roofing solution tailored specifically to the clients and stakeholders needs.
Outcome
Our clients, all relevant stakeholders, and all interested parties involved in the projects appreciated the adherence to the planned schedule, the high level of communication, and the efficiency in which the works were completed. The results of the completed product, and the coordination and communication were the perfect finish to these successful projects.
Construction projects don’t have to be hard or stressful. Let our qualified construction team manage your next commercial project.



Savil Projects acknowledge the Ngunnawal people as the traditional owners of the land on which our business operates. We recognise their continuing connection to land, waters and culture and pay respect to their elders past, present and emerging.